БесплатноНе проверенMCP server for controlling Microsoft Project via COM automation — 79 tools for task, resource, schedule, and baseline management
Описание
MCP server for controlling Microsoft Project via COM automation — 79 tools for task, resource, schedule, and baseline management
README
Control Microsoft Project via COM automation through the Model Context Protocol (MCP).
Prerequisites
- Windows with Microsoft Project installed (tested on MS Project 16.0)
- Python 3.10+
- mcp package:
pip install mcp - pywin32 for COM:
pip install pywin32 - python-dateutil (optional, for
add_recurring_task):pip install python-dateutil
Quick Start
Start MS Project and open a project file (or the server will create one).
Register in your
claude_desktop_config.json:
{
"mcpServers": {
"msproject": {
"command": "python",
"args": ["/path/to/msproject/server.py"]
}
}
}
- Run standalone (for testing):
python server.py
Tool Inventory (99 tools)
Project Management (7)
| Tool | Description |
|---|---|
open_project |
Open an existing .mpp file |
new_project |
Create a new blank project |
get_project_info |
Read project metadata and summary stats |
set_project_properties |
Update title, manager, start date, etc. |
save_project |
Save current project |
save_project_as |
Save as .mpp or .xml |
close_project |
Close the active project |
Task Queries (9)
| Tool | Description |
|---|---|
get_tasks |
List tasks with optional filters |
get_task |
Get a single task by UniqueID |
get_critical_path |
Return critical-path tasks |
get_tasks_by_rag |
Filter tasks by RAG status (Text1) |
get_overdue_tasks |
Incomplete tasks past their finish date |
get_tasks_by_resource |
Tasks assigned to a named resource |
search_tasks |
Full-text search across task names |
get_progress_summary |
Dashboard: progress, RAG counts, overdue |
get_wbs_structure |
Hierarchical WBS tree |
Task Mutations (12)
| Tool | Description |
|---|---|
update_task |
Update any task field (incl. priority, task type) |
bulk_update_rag |
Mass RAG status update |
bulk_update_tasks |
Mass field updates across tasks |
add_task |
Add a single task |
bulk_add_tasks |
Add many tasks at once (JSON array) |
add_recurring_task |
Create recurring task occurrences (daily/weekly/monthly) |
delete_task |
Remove a task |
set_task_mode |
Toggle auto/manual scheduling |
bulk_set_task_mode |
Mass scheduling mode update |
set_constraint |
Set scheduling constraint (ASAP/ALAP/SNET/etc.) |
clear_estimated_flags |
Clear estimated flag on all tasks |
indent_task |
Indent or outdent a task |
Dependencies (4)
| Tool | Description |
|---|---|
add_predecessor |
Create FS/SS/FF/SF link with optional lag |
bulk_add_predecessors |
Mass predecessor creation |
remove_predecessor |
Delete a dependency link |
get_task_dependencies |
Show predecessors and successors |
Resources (7)
| Tool | Description |
|---|---|
get_resources |
List all resources in the pool |
add_resource |
Add a work/material/cost resource |
assign_resource |
Assign a resource to a task |
update_resource |
Modify resource properties |
delete_resource |
Remove a resource (clears assignments) |
set_resource_calendar |
Assign a specific calendar to a resource |
get_resource_availability |
Allocation vs capacity per period |
Resource Assignments (3)
| Tool | Description |
|---|---|
bulk_assign_resources |
Mass resource assignment |
remove_resource_assignment |
Unassign a resource from a task |
get_resource_workload |
Workload and conflict detection for a resource |
Resource Rate Tables (2)
| Tool | Description |
|---|---|
get_resource_rate_tables |
Read cost rate tables A-E for a resource |
set_resource_rate_table |
Set or add rate entries in a cost rate table |
Custom Fields (3)
| Tool | Description |
|---|---|
rename_custom_fields |
Rename Text1-Text30, Number1-Number20, etc. |
update_custom_fields |
Set custom field values on a task |
get_custom_field_values |
Read all values of a custom field |
Import / Export (6)
| Tool | Description |
|---|---|
import_xml |
Import from MS Project XML |
export_xml |
Export to MS Project XML |
export_csv |
Export tasks to CSV with column selection |
snapshot_to_json |
Full project snapshot as JSON |
snapshot_diff |
Compare two JSON snapshots — additions, deletions, changes |
insert_subproject |
Insert a subproject file |
Calendars (7)
| Tool | Description |
|---|---|
get_calendars |
List all project calendars |
create_calendar |
Create a new calendar (optionally copy from existing) |
delete_calendar |
Remove a base calendar |
set_calendar_exception |
Add exception dates (holidays) to a calendar |
delete_calendar_exception |
Remove a specific exception from a calendar |
list_calendar_exceptions |
List all exceptions on a calendar |
set_project_calendar |
Switch the project base calendar |
Calendar Working Hours (1)
| Tool | Description |
|---|---|
set_working_hours |
Modify working hours for a specific day of the week |
Scheduling & Analysis (12)
| Tool | Description |
|---|---|
get_schedule_analysis |
Critical path length, float analysis |
validate_schedule |
Find scheduling issues (missing links, etc.) |
calculate_project |
Recalculate the schedule after manual changes |
get_milestone_report |
Upcoming and overdue milestones |
level_resources |
Run MS Project resource leveling |
find_available_slack |
Tasks with free slack above threshold |
get_constraints |
Read non-default constraints on all tasks |
set_task_calendar |
Assign a calendar to a specific task |
set_task_hyperlink |
Set a hyperlink on a task |
get_critical_path_sequence |
Ordered critical path chain from start to finish with driving links |
get_critical_tasks_for_period |
Critical tasks and milestones within a date range (e.g. Q2) |
what_if_delay |
Simulate delaying a task — shows project impact, newly critical tasks, slack loss |
Status Date & Progress Updates (2)
| Tool | Description |
|---|---|
update_project |
Mark all tasks complete through a date (weekly PMO ritual) |
reschedule_incomplete_work |
Move remaining work to start after a given date |
Timephased Data (1)
| Tool | Description |
|---|---|
get_timephased_data |
Period-by-period work/cost data (for S-curves, cash flow) |
Baselines & Earned Value (4)
| Tool | Description |
|---|---|
save_baseline |
Save baseline (0-10) |
clear_baseline |
Clear a saved baseline |
compare_baselines |
Compare two baselines or baseline vs current |
get_earned_value |
BCWS, BCWP, ACWP, SPI, CPI per task |
Variance & Reporting (1)
| Tool | Description |
|---|---|
get_variance_report |
Schedule + cost variance per task vs a baseline |
Cost & Work (2)
| Tool | Description |
|---|---|
get_cost_summary |
Budget vs actual cost breakdown |
get_actual_work |
Actual vs remaining work hours per task |
Progress Tracking (2)
| Tool | Description |
|---|---|
get_progress_by_wbs |
Completion % rolled up by WBS level |
get_dependency_chain |
Walk predecessor/successor chains |
Advanced Operations (8)
| Tool | Description |
|---|---|
set_deadline |
Set deadline indicator on a task |
bulk_set_deadlines |
Mass deadline assignment |
set_task_active |
Activate/inactivate a task |
dry_run_bulk_update |
Preview bulk changes without applying |
move_task |
Reorder a task after another |
copy_task_structure |
Duplicate a task and its subtree |
cross_project_link |
Create inter-project dependency |
undo_last |
Undo recent operations (up to 10) |
Multi-Project (3)
| Tool | Description |
|---|---|
list_projects |
List all open projects |
switch_project |
Switch active project by name or index |
apply_filter |
Apply a built-in or custom filter |
Filtering & Grouping (2)
| Tool | Description |
|---|---|
filter_tasks |
Advanced multi-field filtering |
group_tasks_by |
Group tasks by any field with aggregation |
Connectivity (1)
| Tool | Description |
|---|---|
health_check |
Lightweight COM connectivity test — version, project status |
Enriched Task Data
Every task query (get_task, get_tasks, etc.) returns a rich dict with 35+ fields including:
| Field | Description |
|---|---|
actual_start / actual_finish |
When work actually began/ended |
remaining_duration_days |
How much work is left |
total_slack_days / free_slack_days |
Schedule flexibility |
deadline |
Soft deadline indicator |
priority |
Leveling priority (0–1000) |
constraint_type / constraint_date |
Scheduling constraint |
manual |
Auto vs manual scheduling |
type |
FixedUnits / FixedDuration / FixedWork |
hyperlink / hyperlink_text |
Task hyperlink |
Known Limitations
- COM proxy staleness: When multiple projects are open, switching projects invalidates existing COM references. Always call
switch_projectbefore operating on a different file. - Undo stack:
undo_lastsupports up to 10 consecutive undos. MS Project's COM undo is less reliable than the UI's. - File locking: Only one process can hold the COM connection. Don't open MS Project's GUI dialogs while the server is active.
- Timezone-aware dates: COM may return timezone-aware datetimes. The server normalizes these via
_to_naive()for safe comparisons. - Recurring tasks: MS Project's
RecurringTaskInsertis a dialog-only COM method. Theadd_recurring_tasktool simulates recurrence by creating individual occurrences under a summary task. Requirespython-dateutil. - Timephased data:
get_timephased_datacan be slow on large date ranges. Keep queries to reasonable periods (weeks/months, not years).
Tests
# Run all phases
python tests/test_new_tools.py # 11 tests (core CRUD)
python tests/test_phase2.py # 10 tests (resources, baselines, WBS)
python tests/test_phase3.py # 15 tests (custom fields, calendars, scheduling)
python tests/test_phase4.py # 23 tests (advanced ops, multi-project, filtering)
python tests/test_phase5.py # 11 tests (bug fixes, cost/work tracking)
python tests/test_phase6.py # 75 tests (timephased data, calendar mgmt, variance)
python tests/test_phase7.py # 57 tests (critical path intelligence, what-if)
202 tests total across 7 test suites. All tests require MS Project to be running (they create and close temporary projects).
Architecture
Single-file server (server.py, ~5,200 lines) using the FastMCP framework. All COM calls go through get_app() / get_proj() helpers. Dates are normalized with _to_naive() and formatted with _fmt_date().
Development Phases
| Phase | Tools | Focus |
|---|---|---|
| 1–2 | 25 | Core CRUD, dependencies, resources |
| 3 | 44 | Custom fields, calendars, scheduling analysis |
| 4 | 65 | Advanced operations, multi-project, filtering |
| 5 | 79 | Bug fixes, cost/work tracking |
| 6 | 96 | Timephased data, calendar management, resource availability, variance reporting |
| 7 | 99 | Critical path intelligence: ordered sequence, period filtering, what-if analysis |
Contributing
See CONTRIBUTING.md for development setup, conventions, and how to submit changes.
License
This project is licensed under the MIT License — see LICENSE for details.
Установка MS Procject
У этого сервера нет опубликованного пакета — он собирается из исходников. Открой репозиторий и следуй инструкции в README.
▸ github.com/elsahafy/MS-Procject-MCPFAQ
MS Procject MCP бесплатный?
Да, MS Procject MCP бесплатный — установка в пару кликов через Unyly без оплаты.
Нужен ли API-ключ для MS Procject?
Нет, MS Procject работает без API-ключей и переменных окружения.
MS Procject — hosted или self-hosted?
Self-hosted: сервер запускается локально на твоей машине командой из раздела установки.
Как установить MS Procject в Claude Desktop, Claude Code или Cursor?
Открой MS Procject на unyly.org, выбери вкладку своего клиента (Claude Desktop, Claude Code, Cursor) и нажми Install — конфиг сгенерируется автоматически, без правки JSON.
Похожие MCP
Notion
Read and write pages in your workspace
автор: NotionLinear
Issues, cycles, triage — from Claude
автор: LinearGoogle Drive
Search and read your Drive files
автор: Googlemindsdb/mindsdb
Connect and unify data across various platforms and databases with [MindsDB as a single MCP server](https://docs.mindsdb.com/mcp/overview).
автор: mindsdbCompare MS Procject with
Не уверен что выбрать?
Найди свой стек за 60 секунд
Автор?
Embed-бейдж для README
Похожее
Все в категории productivity